Hwy 57 / W 1st Street Expansion Project

Beginning Wednesday, June 2nd, 2021, the Iowa DOT’s contractor, PCI, will be continuing with construction by reconstructing the southeastern corner of the Hudson Road intersection and also continuing with work on the south side of HWY 57 between Hudson Road and Francis Street. In order for the contractor to begin, a full closure of the adjacent lanes will be required until paving is complete.

 

East & Westbound traffic on HWY 57 and North & Southbound traffic on Hudson Road will be maintained throughout construction. This construction will result in restricted turning movements at the Hudson Road intersection. Trailered vehicles should choose alternative routes to avoid turning at the intersection. The lane closures for this phase will be in effect for approximately one (1) month, depending on the weather.

 

For safety's sake, please stay away from the construction area. Heavy equipment will be moving back and forth on the closed section of street. Attached is a map of the closure area highlighted.

 

If you have any questions or concerns during the course of construction, please contact Ron Loecher with the Iowa DOT listed here:

Ron Loecher, PE, Resident Engineer, 641-394-3161, Ron.Loecher@iowadot.us

 

Regards,

 

Matthew Tolan, EI

Civil Engineer II

 

City of Cedar Falls

Department of Public Works | Engineering Division

220 Clay Street | Cedar Falls, Iowa 50613

Office: 319.268.5164 | Cell: 319.575.2864 | Fax: 319.268.5197

Email | Website | Facebook | Twitter 

HWY 57 - Stage 3B - 1 of 2HWY 57 - Stage 3B - 2 of 2

Beginning Monday, April 12th, 2021, the Iowa DOT’s contractor, PCI, will be continuing with construction by reconstructing the southwestern corner of the Hudson Road intersection and also by starting removals on the south side of HWY 57 between Hudson Road and Francis Street. In order for the contractor to begin, a full closure of the adjacent lanes will be required until paving is complete.

 East & Westbound traffic on HWY 57 and North & Southbound traffic on Hudson Road will be maintained throughout construction. This construction will result in restricted turning movements at the Hudson Road intersection, trailered vehicles should choose alternative routes to avoid turning at the intersection. The lane closures for this phase will be in effect for approximately one (1) month, depending on the weather.

 For safety's sake, please stay away from the construction area. Heavy equipment will be moving back and forth on the closed section of street. Attached is a map of the closure area highlighted.

 If you have any questions or concerns during the course of construction, please contact Ron Loecher with the Iowa DOT listed here:

Ron Loecher, PE, Resident Engineer, 641-394-3161, Ron.Loecher@iowadot.us

 Regards,

 Matthew Tolan, EI

Civil Engineer II

 City of Cedar Falls

Department of Public Works | Engineering Division

220 Clay Street | Cedar Falls, Iowa 50613

Office: 319.268.5164 | Cell: 319.575.2864 | Fax: 319.268.5197

EmailWebsiteFacebookTwitter