North Cedar Heights Area Reconstruction

Thank you for your patience during this plan development process. Now that we are entering the winter season, there will be some City of Cedar Falls Public Works crews beginning the tree clearing work along the northern edge of West Ridgewood Drive. This work is anticipated to begin the week of December 19th. On the back of this sheet is an image depicting the approximate location for the tree removal area.

As discussed in the public information meeting that was held in September, this area of the slope has failed and will be corrected during the first phase of construction next year. By clearing the trees outside of migratory bird season, we can prevent any significant environmental disturbances. After the slope is corrected by construction, the slope will be seeded with a prairie seed mixture to provide the best slope stability moving forward.

As a general update on the planned reconstruction for next year, we are anticipating a bidding date in February, and will be holding one final Project Information Meeting for the residents that will be directly impacted by the construction on Timber Drive and West Ridgewood Drive in March. At this meeting, we will be able to share the most accurate preconstruction information possible.

Lastly, for more project information, please visit www.cedarfalls.com/1699/North-Cedar-Heights-Area-Reconstruction 

Slope Clearing for North Cedar Heights Area Reconstruction

Click here for more information and to view the slideshow from the Public Information Meeting.


PUBLIC INFORMATION MEETING NOTICE

North Cedar Heights Area Street Reconstruction Projects

Date: Thursday, September 1, 2022

Location: Cedar Falls Public Works Facility - 220 Technology Parkway

Time: 5:30 PM - 7:00 PM

The City will be holding a follow-up neighborhood meeting to share information with citizens regarding the reconstruction of streets in the North Cedar Heights area over the next five years. These streets include: Cherry Lane, Edwards Avenue, E., and W. Ridgewood Drive, Greenwood Avenue, Oakland Avenue, Picturesque Drive, Timber Drive, and Woodland Avenue.

Updated information will be provided on the design and construction-related items such as repaving, water main, storm sewer, and sanitary sewer. More specific information on the planned reconstruction of Phase 1 (West Ridgewood Drive from Greenwood Avenue to Cherry Lane, and Timber Drive from Grand Boulevard to Greenwood Avenue) will be available at this time.

All interested persons are invited to attend this meeting. Doors will open at 5:30 PM with a brief presentation reviewing design requirements, scope, and expectations of the project, construction phasing, and a 2023 construction timeline. Afterward, a large plan-view map will be available for viewing. During this time, City officials will be available to answer any questions. 

If you have any questions prior to the meeting, or after, please contact the Cedar Falls Engineering Division at (319) 268-5161.